Drainage Upgrade To Ease Flood Risk In South Mackay

Last Thursday, Council started work to clear trees and other vegetation from the large open drain, which runs alongside Bridge Road.

Over the course of several years, mangroves have established in the tidal drain on Bridge Road, South Mackay.

Director Infrastructure and Operations with Mackay Regional Council, Simon Taylor said the clearing is expected to improve the efficiency of the drain during flood events where tidal conditions are favourable.

“There are restrictions around the removal of mangroves,” Mr Taylor said.

“These types of trees can’t be cleared without special approvals from the State
Government, which we have obtained.”

Mr Taylor said the aim is to complete clearing before the start of the wet season.

“Having this drain cleared will assist flood water to drain away from our
residential areas and important community assets under favourable tidal conditions.

“It is important to note that the drainage works do not remove flood risk associated with potential storm surge events accompanying tropical cyclones and residents of low-lying areas are encouraged to review our Emergency Action Guide

"Council will continue to work closely with the State Government on the future maintenance of the drain."

The section between Casey Avenue and Leisure Court will be cleared first.

The work is expected to take about two months, weather and tides permitting.

Council has begun clearing mangroves and vegetation from the Bridge Road drain in South Mackay to improve flood flow ahead of the wet season. Photo supplied