This week
Season to date
Cane crushed
97,268
968,604
Average bin weight
9.66
9.61
CCS
14.38
13.99
Cane variety performance for region
Variety
%
CCS
Variety
%
CCS
Q208
20.8
15.01
Q253
9.7
13.96
Q240
15.3
14.13
KQ228
5.1
13.89
Q183
14.1
14.55
SRA12
2.1
14.14
SRA9
10.2
14.79
Q247
1.1
13.47
Comments
Proserpine Mill processed 97,268 tonnes of cane for the week, which is the highest factory throughput since 2020. Thanks to all sectors of the industry for working together to achieve this great result.
We’ve now processed close to 970,000 tonnes of cane for the season, representing about 56 per cent of the total estimated crop.
The average weekly CCS came in slightly below budget at 14.38 units.
The highest CCS was 17.16 units from a rake of ratoon Q208 from the Kelsey Creek productivity district.
Please remember to use your train brain and always take care around our cane rail network.
A fully loaded cane train can take up to one kilometre to pull up. Our cane trains work around the clock, seven days a week.
Peter Luke
Cane Supply Manager
Proserpine Region