Alfred Street Water Main Renewal

Mackay Regional Council will be replacing an aged water main at Alfred Street, between Wellington and Peel streets.
Works began early this week (from Monday, November 25), and are expected to be complete by late-January, 2025, weather permitting.
The centre parking on Alfred Street, in this section, will be unavailable for the duration of the work.
While works are underway, a partial road closure will be in place, with the westbound lane (towards Peel Street) closed during working hours for the duration of the project.
The eastbound lane (towards Wellington Street) will remain open.
Works will be undertaken from Monday to Friday, 6am to 6pm. Some weekend and night work may also be required.
There may be some intermittent noise and dust disturbances associated with these works.
Council apologises for any inconvenience caused and appreciates your patience during these essential works.
For enquiries, please contact council on 1300 MACKAY (622 529).